Recent Progress
Met with Headquarters Geotechnical and Bridge & Structures to finalize wall and culvert design issues.
A public open house was held at the end of January. Comments on the Joint Aquatic Resources Permit Application have been received and will be responded to in March.
Comments on our application to the state Parks Department to construct environmental mitigation work for our project in Lake Sammamish State Park have been received and will be responded to.
Design and construction offices have done a joint review and are updating the construction cost estimate.
Purchasing of Real Estate property required for this project is continuing.
|