This project will widen SR 900 from SE 78th vicinity north to Newport Way from 2 to 4 lanes and a two way left turn lane. The purpose is to add width and capacity to SR 900 to improve operations and safety.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

A Cost Risk Assessment was completed for this project.  The project estimate is $5 million over the budget amount.  The project has been reviewed for cost saving opportunities and a preferred alternative has been identified.

Design Construction Impacts
Working with the city of Issaquah to determine final channelization layout and location of pedestrian facilities.

Environmental Impacts / Compliance
Discussing phosphorus removal requirements with permitting agency to determine impacts on size of stormwater treatment ponds.  A report has been prepared analyzing the performance of previously constructed treatment facilities and will be presented to the Multi Agency Permitting Team.

Impacts to Traffic
This project is targeted to improve efficiency of traffic operation.   Construction will require non-peak lane closures and temporary detours.

Project Milestones Scheduled Attained Milestone Outlook
Begin Prelim Engineering (nickel portion) Aug 03 Sep 03  
Environmental Complete Dec 06    BA and SEPA are being reviewed for submittal to the regulatory agencies.
Right of Way Certified Mar 07    
Contract AD Apr 07  

 

Open to Traffic Summer 09    
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $2.0 m 13.6%
Right-of-Way $1.8 m 12.2%
Construction $10.9 m 74.2%
Funded Project Costs $14.7 m 100%

Nickel funds included in above costs

$14.7 m 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

John E. Johnson, WSDOT Project Engineer (206) 440-4552 or
E-mail:  JohnJoh@wsdot.wa.gov