SR 9 - SR 522 to 212th St. SE - SR 524 - Stage 1B and 2 - Complete May 2008

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
SR 9 – SR 522 to 212th St. SE; Widening
(Stages 1b & 2), North Woodinville

Project Description
This project adds lanes and enhances safety on 1.8 miles of congested state highway.

Contractor/Consultant
Wilder Construction of Everett.

Recent Progress

Whistle Creek Alignment is complete
Walls 5, 7, 8, 9 are complete
Paved the eastside of SR 9 from SR522 to Cutthroat Creek
Shift Traffic to the eastside from SR522 to Cutthroat Creek
Installed temporary signals at SR9/SR524
Installed creek bypass system at Cutthroat Creek, Great Danes Creek, and Whistle Creek

Design Construction Impacts

Utility relocation work continues to be a concern for potential schedule delay and increase construction cost.  We are working with the Utility companies and the contractor to minimize the impact.

 

More than anticipate ground water and offsite water has impeded the contractor ability to do the work.  Dewatering system and French trench were installed to help mitigate the problem.  However, we anticipate that this problem will be on going and will have cost impact to the project.

Environmental Impacts / Compliance

There were several water quality exceedances on this project.  We are working with the contractor to eliminate/reduce these exceedances.  There were no environmental violations thus far.

Work at Cutthroat Creek and Great Danes Creek will be completed after the September 15, 2006 fish window.  WDFW has granted extension to the fish window to October 31, 2006 for those two locations.  We are working with the Contractor to make sure that all creek work will be done by October 31, 2006 deadline.

Impacts to Traffic

Traffic has experienced narrower lanes and shoulders, slower speeds and occasional stopped traffic in construction work zones during the daytime.  Some night and weekend lane and roadway closures occurred during construction period.  A comprehensive public information effort to share timing of construction activities and traffic impacts has occurred.

Project Milestones Scheduled Attained Milestone Outlook
PE: Start Date  June 1996 June 1996  Project design is complete.
RW: Certification Date * February 2005  April 2005 * The r/w certification has been completed and the project has been advertised for bids. 
EN: Environmental Approval * February 2005  April 2005 * All Environmental permits have been acquired
AD: Planned Ad Date * February 2005  May 2005

 

OT: Open to Traffic * January 2008   Due to the impact of ground water and offsite water, we are a month behind on accomplishing one of our milestones; to shift all traffic to the east side of the newly paved road.  We currently have partial traffic shift from SR 522 to Cutthroat Creek.  However, we believe that we can still complete this project and open to traffic by June 2007.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $4.5m 13.1%
Right-of-Way $4.5m 13.1 %
Construction $25.4 m 73.8%
Funded Project Costs $34.1 m 100 %

Nickel funds included in above costs

$29.5 m 85.8 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

John Chi, WSDOT Project Engineer @ (425) 489.5402 Or E-mail: chij@wsdot.wa.gov