SR 9 - SR 522 to 212th St. SE - SR 524 - Stage 1B and 2

Quarterly Project Report Update for Quarter Ending September 2005

Project Title & Location
SR 9 – SR 522 to 212th St. SE; Widening
(Stages 1b & 2), North Woodinville

Project Description
This project adds lanes and enhances safety on 1.8 miles of congested state highway.

Contractor/Consultant
Wilder Construction of Everett.

Recent Progress

The construction contract was awarded to Wilder Construction of Everett in July 2005. Construction activities started in late August 2005. Groundbreaking event was held on 9/22/05.

Crews from Snohomish Public Utility District (SnoPUD) and other Utility companies have started removing trees and relocating their facilities along SR 9 to make room for the highway widening.

Design Construction Impacts

Coordination with adjoining utility companies is ongoing, as well as our continuing efforts with Snohomish County and the Brightwater Treatment Plant design teams. Utility Companies have already started the relocation of their facilities to make room for the widening of the highway.

Environmental Impacts / Compliance

No significant impacts.  This project will meet all applicable permit requirements and avoid any stream or wetland impacts where possible or mitigate for the impact through the creation or enhancement of new wetlands.

 

This project will construct storm water facilities to treat for quality and quantity.  Construction will incorporate use of temporary erosion control measures to minimize impacts.

Impacts to Traffic
Construction activities are underway.  Traffic will experience narrower lanes and shoulders, slower speeds and occasional stopped traffic in construction work zones during the daytime.  Also, some night and weekend lane and roadway closures will occur during the construction period.  A comprehensive public information effort to share timing of construction activities and traffic impacts is underway starting with a public open house meeting in late September. All 4 lanes should be open to traffic by Fall 2007.

Project Milestones Scheduled Attained Milestone Outlook
PE: Start Date  June 1996 June 1996  Project design is complete.
RW: Certification Date * February 2005  April 2005 * The r/w certification has been completed and the project has been advertised for bids. 
EN: Environmental Approval * February 2005  April 2005 * All Environmental permits have been acquired
AD: Planned Ad Date * February 2005  May 2005

 

OT: Open to Traffic September 2007 The project is scheduled to open to traffic by Fall 2007.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $4.2m 12.3%
Right-of-Way $4.6m 13.5 %
Construction $25.3 m 74.2%
Funded Project Costs $34.1 m 100 %

Nickel funds included in above costs

$29.5 m 86.5 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Carl Barker, WSDOT Acting Project Engineer @ (425) 489.5403 Or E-mail: barkerc@wsdot.wa.gov