SR 9 - SR 522 to 212th St. SE - SR 524 - Stage 1B and 2

Quarterly Project Report Update for Quarter Ending March 2005

Project Title & Location
SR 9 – SR 522 to 212th St. SE; Widening
(Stages 1b & 2), North Woodinville

Project Description
This project adds lanes and enhances safety on 1.8 miles of congested state highway.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

Delays in design completion and concerns about receiving environmental permits and completing right of way acquisition in time has caused the project advertisement to slip two months from February to April 2005. This delay should not compromise the construction season and open to traffic date.  Acquisition of Right of Way parcels by the real estate consultant continues with good progress to meet the current ad date.  The design team and environmental specialists have completed addressing permitting agencies comments and all environmental permits are expected in early April. Coordination with Utility Companies to relocate their facilities is on going.

As early as April 2005, crews from Snohomish Public Utility District (SnoPUD) will begin removing trees along SR 9 to make room for the utilities relocation and the highway widening.

Design Construction Impacts

The design team continues to monitor progress on the time critical activities of environmental permits and Right of  Way acquisition.  As mentioned in the last report, the design team has prepared alternative construction sequences in order to respond to any potential delays that might come from these activities.  Coordination with adjoining utility companies is ongoing, as well as our continuing efforts with Snohomish County and the Brightwater Treatment Plant design teams.

Environmental Impacts / Compliance

No significant impacts.  This project will meet all applicable permit requirements and avoid any stream or wetland impacts where possible or mitigate for the impact through the creation or enhancement of new wetlands.

This project will construct storm water facilities to treat for quality and quantity.  Construction will incorporate use of temporary erosion control measures to minimize impacts.

Impacts to Traffic
Construction will start in the summer of 2005.  Traffic will experience narrower lanes and shoulders, slower speeds and occasional stopped traffic in construction work zones during the daytime.  Also, some night and weekend lane and roadway closures may occur during the construction period.  Anticipate a comprehensive public information effort to share timing of construction activities and traffic impacts.  All 4 lanes should be open to traffic by Summer 2007.

Project Milestones Scheduled Attained Milestone Outlook
PE: Start Date  June 1996 June 1996  Project design is underway.
RW: Certification Date * February 2005   * Delays in right of way purchase has caused the r/w certification to be delayed to April 2005. 
EN: Environmental Approval * February 2005   * Environmental permits are expected in April 2005. The delay in receiving the permits was due to the late submittal of the permit application. The permit application was delayed last year due to the late discovery of additional wetlands and a fish bearing stream/ditch.
AD: Planned Ad Date * February 2005   * Delays in design completion and concerns about receiving environmental permits and completing right of way acquisition in time has caused the project advertisement to slip two months from February to April 2005. The project is currently on schedule to meet the new ad date of April 2005.
OT: Open to Traffic June 2007 The slight delay to ad date will have no impact on the open to traffic date. The project is scheduled to open to traffic by summer 2007.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $4.2m 12.3%
Right-of-Way $4.6m 13.5 %
Construction $25.3 m 74.2%
Funded Project Costs $34.1 m 100 %

Nickel funds included in above costs

$29.5 m 86.5 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Sharif Shaklawun, WSDOT Project Engineer @ (206) 440-4272 Or E-mail: Shaklas@wsdot.wa.gov