Design Construction Impacts
Utility relocation work and right of way acquisition were a concern for the potential schedule delay and increase construction cost. However, we have worked with the contractor to resolve these issues.
More than anticipate ground water and offsite water has impeded the contractor ability to do the work. Dewatering system and French trench were installed to help mitigate the problem. However, we anticipate that this problem will be on going and will have cost impact to the project.
|