|
Design Construction Impacts
Utility relocation work continues to be a concern for potential schedule delay and increased construction cost. We are working with the Utility companies and the contractor to minimize impacts.
More than anticipated ground water and offsite water has impeded the contractor's ability to do the work. Dewatering system and French trench were installed to help mitigate the problem. However, we anticipate that this problem will be ongoing and will have cost impacts to the project.
There is a potential risk of schedule and cost impact for Wall 1 and SR522 off-ramp widening work due to limited work space, nearby sensitive areas, offsite and ground water and working through the wet winter. We are working with the contractor to minimize the potential cost and schedule impact.
|