Skip Top Navigation

SR 9 -SR 522 to 212th St. SE - SR 524 Stage 1 B and 2 - Current Photos

June 2008


In June 2008, crews striping the ramp from SR 9 to westbound SR 522. Crews have completed the majority of work for the project and are now waiting for a few dry nights to finish minor touch-ups.


Drivers will notice new pavement and striping on the ramp from eastbound SR 522 to northbound SR 9.

April 2008


Dry, warm weather on Tuesday, April 1 allowed crews to finish paving the ramp from SR 9 to SR 522.


Paving the ramp to SR 522 was an important milestone in the SR 9 project. Once paving was complete, crews had to wait for the pavement to cure before completing permanent striping.


Crews took advantage of a dry day in April to pave the ramp to SR 522.

Photo Gallery:
November 2007
August 2007
March/April 2007
October 2006
September 2006
Before and After