Recent Progress
The Final Stormwater Report is pending completion of a Flood Equalization Study, which is being completed by Parametrix. The Environmental permit applications have been returned by the resource agencies with comments. Region Environmental is addressing agency comments and preparing to resubmit for agency approval. The utility company relocation plans have been initated. The 60% PS&E package was submitted by the consultant on 6/6/06. Review comments have been returned to the consultant. 100% PS&E package is due on August 14th.
We are anticipating approximately $812K ($150K PE and $662 CN) in total budget overruns. Based on inflation, this overrun could grow to $1.2M by the mid-point of construction.
The construction cost for the three combined projects is over budget by $662K at the 60% level of PE development. This overrun is primarily due to the large price increases for fuel oil associated with asphalt and haul items of work. Steel price adjustments were also necessary due to the lack of availability on the commercial market. Design is estimated to be over budget by $150K ($100K consultants, $50K WSDOT) due to redesigns and additional work that has been required to get the project Ad ready and obtain environmental permits. R/W is anticipated to be delivered on budget.
While we have looked at a number of options to reduce the budget overruns, we have decided to accept the overruns and seek additional funding. Our justification is due to the safety nature of the project improvements, the long-term need for the improvements and the reality that WSDOT will not be back in this area with construction improvements in the foreseeable future.
|