SR 9 - 212th SE to 176th SE (Stage 3)

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
SR 9 - 212TH St. SE to 176th St. SE (Stage 3)
Clearview

Project Description
This project adds lanes and enhances safety on 2.7 miles of congested state highway.

Contractor/Consultant
This project is not yet advertised or awarded.

Recent Progress
WSDOT has begun preliminary survey work along this portion of Highway 9.  An updated traffic study, delineation of wetlands and streams have been completed. Design team is working on alternative analysis to determine the roadway footprint and right of way needs. Roadway footprint and right of way plans will be ready by the end of summer 2007. Last June the project cost estimate was updated to reflect recent construction cost escalations.  A Cost Risk Assessment was performed on this project in November 2006 to validate the June 2006 cost update.

Design Construction Impacts

Traffic volumes and development along this highway corridor have grown much faster than was anticipated when the need for this project was first identified over ten years ago.  In response to this, WSDOT has advanced some of the design funding for this project by one year. 

 

Environmental Impacts / Compliance

This project will meet all applicable permit requirements and avoid any stream or wetland impacts where possible or mitigate for the impact through the creation or enhancement of new wetlands.

 


This project will construct storm water facilities to treat for quality and quantity.  Construction will incorporate use of temporary erosion control measures to minimize impacts.

Impacts to Traffic
Construction will start in the summer of 2011.  Traffic will experience narrower lanes and shoulders, slower speeds and occasional stopped traffic in construction work zones during the daytime.  Also, some night and weekend lane and roadway closures may occur during the construction period.

Project Milestones Scheduled Attained Milestone Outlook
Environmental Permits Spring 2009
Right of Way Purchased Fall 2010
Finish Contract Plans Fall 2010
Contract Advertised Fall 2010
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $6.3 7.7 %
Right-of-Way $30.0 36.8 %
Construction $45.2 55.5 %
Funded Project Costs $81.5 100.0 %

Nickel funds included in above costs

$81.4 99.9 %

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Sharif Shaklawun, WSDOT Project Engineer @ (206) 440-4272 Or E-mail: ShaklaS@wsdot.wa.gov