SR 9 - 212th Street SE Vic to SR 96

Quarterly Project Report Update for Quarter Ending June 2004

Project Title & Location
SR 9 / 212th St SE Vic. to SR 96/Lowell- Larimer Rd. Vic.

Project Description
This project will construct northbound and southbound left-turn lanes on SR 9 at 188th St SE, a two-way left-turn lane on SR 9 at 172nd St SE, and a southbound lane on SR 9 at SR 96/Lowell-Larimer Rd. A traffic signal will be installed at 164th St SE.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
The design of this project will begin in April, 2004

Design Construction Impacts
There are no impacts at this time.

Environmental Impacts / Compliance
Environmental impacts and improvements have not been identified at this time.

Impacts to Traffic
The finished project will improve traffic flow and safety on this section of highway.

Project Milestones Scheduled Attained Milestone Outlook
Begin Design April 2004 No issues at this time.
Contract Advertisement December 2007 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.90 15.1%
Right-of-Way $1.21 20.3%
Construction $3.84 64.6%
Funded Project Costs $5.95 100%

Nickel funds included in above costs

$4.93 82.9%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Marlin Lenssen, WSDOT Project Engineer @ (425)339-1719 Or E-mail: lenssmj@wsdot.wa.gov