Recent Progress
We are proposing to re-define the scope from the March 2005 QPR by NW Region Traffic to better address the current safety needs intended by this project. In addition, this project has added the design of a wetland mitigation site which includes additional r/w acquisition for a mitigation site (see “Environmental Impacts/Compliance” ).
The budget and schedule have been re-evaluated and based on the lack of workforce, it is recommended that this project be completed, utilizing a Consultant. The estimated budget includes the cost of using a Consultant to complete the design of this project through PS&E. However, it is recommended that the hydraulic design and the preparation of the right of way plans be completed in house since the hydraulics is at 75% completion and the r/w plans are 50% completion.
The current budget is adequate for the proposed revisions to this project, however, funds need to be reallocated with $163,745 transferred from CN to PE.
|