SR 9 - 108th Street NE (Lauck Road) - Complete January 2008

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location

SR 9 - 108th Street NE (Lauck Road)

MP 21.78 to MP 22.02

Project Description
This project will widen SR 9 by constructing a northbound left turn lane, a southbound left turn lane and a southbound right turn lane. The project will also perform minor safety improvements, install illumination and update signing.

Contractor/Consultant
Project awarded.

Recent Progress
Project has been advertised and bids were opened in late March.

Design Construction Impacts
 Preliminary Engineering cost were slightly higher ($20k) than projected last quarter. However, construction bids were significantly lower ($109k) than anticipated.

Environmental Impacts / Compliance
No wetland impacts are expected.  Best Management Practices will be used to minimize impacts during construction.

Impacts to Traffic
Nighttime (6pm to 6am) single lane closures will be necessary during construction.

Project Milestones Scheduled Attained Milestone Outlook
Begin PE October 2004 October 2004
Right of Way December 2006 January 2007
Environmental Permits December 2006 April 2007
Contract Advertised January 2007 April 2007
Open to Traffic February 2008 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.45 m 24.3%
Right-of-Way $0.10 m 5.4%
Construction $1.30 m 70.3%
Funded Project Costs $1.85 m 100%

Nickel funds included in above costs

$1.20 m 64.9%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

For additional information please contact MarlinLenssen at (425)225.8796 or at lenssmj@wsdot.wa.gov