Project Description
This project will widen SR 9 by constructing a northbound left turn lane, a southbound left turn lane and a southbound right turn lane. The project will also perform minor safety improvements, install illumination and update signing.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress

The Right of Way Plan with Access revision is nearing approval.  The Drainage design is also nearing completion. 

Design Construction Impacts
The current budget for this project is short $340k ($200k for PE and $140k for CN).  The current budget is based on a 25% Snohomish County participation.  The 25% participation was calculated using peak hour volumes, which is incorrect.  When using the correct ADT volumes, the county participation is 14.4%.

Environmental Impacts / Compliance

No wetland impacts are expected.  Best Management Practices will be used to minimize impacts during construction.

Impacts to Traffic

Daytime (9am to 3pm) and nighttime (6pm to 6am) single lane closures will be necessary during construction.

Project Milestones Scheduled Attained Milestone Outlook
Begin PE October 2004 October 2004  
Right of Way December 2006 Finalizing Right of Way Plan.
Environmental Permits December 2006 No issues at this time.
Contract Advertised January 2007 No issues at this time.
Open to Traffic February 2008 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.28 m 20.1%
Right-of-Way $0.18 m 12.9%
Construction $0.93 m 67.0%
Funded Project Costs $1.39 m 100%

Nickel funds included in above costs

$0.81 m 58.3%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects