Project Title & Location
SR 9 - 108th Street NE (Lauck Road)
MP 21.78 to MP 22.02
|
Project Description
This project will widen SR 9 by constructing a northbound left turn lane, a southbound left turn lane and a southbound right turn lane. The project will also perform minor safety improvements, install illumination and update signing.
|
|
Contractor/Consultant
Project not yet advertised or awarded.
|
|
Recent Progress
Right of way and limited access acquisition is progressing. Higher then expected groundwater has impacted the drainage design.
|
|
Design Construction Impacts
The current budget for this project is short $286k ($158k for PE, $10K for RW and $119k for CN). The current budget is based on a 26.9% Snohomish County participation. The 26.9% participation was calculated using peak hour volumes, which was incorrect. When using the correct AWDT volumes, the county participation is 14.4%. The agreement is with Snohomish County for approval.
|
|
Environmental Impacts / Compliance
No wetland impacts are expected. Best Management Practices will be used to minimize impacts during construction.
|
Impacts to Traffic
Daytime (9am to 3pm) and nighttime (6pm to 6am) single lane closures will be necessary during construction.
|