SR 9 - 108th Street NE (Lauck Road) - Complete January 2008

Quarterly Project Report Update for Quarter Ending December 2005

Project Title & Location

SR 9 - 108th Street NE (Lauck Road)

MP 21.78 to MP 22.02

Project Description
This project will widen SR 9 by constructing a northbound left turn lane, a southbound left turn lane and a southbound right turn lane. The project will also perform minor safety improvements, install illumination and update signing.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
The channelization plan was revised, approved and signed by NWR Traffic on October 25, 2005.  The revision shortened the right turn lane on east bound 108th to eliminate the impacts to an existing driveway.

Design Construction Impacts
The current budget for this project is short $390,255 ($252,191 for PE and $138,064 for CN).  The current budget is based on a 25% Snohomish County participation.  The 25% participation was calculated using peak hour volumes, which is incorrect.  When using the correct ADT volumes, the county participation is 14.4%.

Environmental Impacts / Compliance

Talent Memo is in review - October 20, 2005.

No wetland impacts.

Impacts to Traffic

Single lane closures will be necessary to accomplish the following work: roadway widening, paving/striping, and install illumination sysyem.

Project Milestones Scheduled Attained Milestone Outlook
Begin PE October 2004 October 2004  
Right of Way January 2006 No impact to schedule.  Limited access east of the intersection needs to be added to the right of way plans.  A driveway in NE corner of intersection is within the proposed limited access.  Cost for relocation of driveway is $140,000 ($103,500 for RW and $36,500 for CN).  Pursuing a deviation to allow the driveway to cross the limited access 
Environmental Permits February 2006 No issues at this time.
Contract Advertised January 2007 No issues at this time.
Open to Traffic March 2007 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.28 m 20.1%
Right-of-Way $0.18 m 12.9%
Construction $0.93 m 67.0%
Funded Project Costs $1.39 m 100%

Nickel funds included in above costs

$0.81 m 58.3%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

For additional information please contact Methqal Abu-Najem at (206)440.4232 or at AbuNajM@WSDOT.WA.GOV