|
Project Title & Location
SR 9 - 108th Street NE (Lauck Road)
MP 21.78 to MP 22.02
|
Project Description
This project will widen SR 9 by constructing a northbound left turn lane, a southbound left turn lane and a southbound right turn lane. The project will also perform minor safety improvements, install illumination and update signing.
|
|
Contractor/Consultant
Project not yet advertised or awarded.
|
|
Recent Progress
The channelization plan was revised, approved and signed by NWR Traffic on October 25, 2005. The revision shortened the right turn lane on east bound 108th to eliminate the impacts to an existing driveway.
|
|
Design Construction Impacts
The current budget for this project is short $390,255 ($252,191 for PE and $138,064 for CN). The current budget is based on a 25% Snohomish County participation. The 25% participation was calculated using peak hour volumes, which is incorrect. When using the correct ADT volumes, the county participation is 14.4%.
|
|
Environmental Impacts / Compliance
Talent Memo is in review - October 20, 2005.
No wetland impacts.
|
Impacts to Traffic
Single lane closures will be necessary to accomplish the following work: roadway widening, paving/striping, and install illumination sysyem.
|