|
Project Title & Location
SR 823 - Goodlander to Harrison Rd - Build Sidewalk
|
Project Description
This project will increase pedestrian and motorist safety by constructing a sidewalk on the east side of SR 823 from Goodlander Road to Harrison Road. The intersection at Goodlander Road will also be improved to allow easier right-turns onto northbound SR 823 and eliminate the "jog" for motorists traveling northbound through the intersection.
|
|
Contractor/Consultant
Granite Northwest, Inc. (dba Superior Paving) of Yakima, WA.
|
|
Recent Progress
The contract was awarded to Granite Northwest, Inc. on November 5, 2007.
|
|
Design Construction Impacts
Construction will begin on March 17, 2008 depending on weather.
|
|
Environmental Impacts / Compliance
SEPA and NEPA documentation were complete on 8/22/06. No permits are required for this project.
|
Impacts to Traffic
One of two northbound lanes of SR 823 is expected to be closed during the day for construction activities.
|