Project Description
When completed this project will provide a direct east-west highway connecting I-5 and SR 7. The Cross-Base Highway will be a new six mile, four lane limited access highway with four signalized intersections and two new interchanges.

Contractor/Consultant
Ceccanti, Inc.

Recent Progress
Two successful weekend closures occurred in October. The travelling public is currently driving on the new alignment. The stormwater ponds and drainage features are currently being installed. The shafts for the noise walls will start in mid-November.

Design Construction Impacts
To date the project has been constructed as designed with only minor changes.

Environmental Impacts / Compliance
Project 1 has minimal impacts to the environment and the proper measures are being implemented as part of the construction.

Impacts to Traffic
Most of the construction work will be completed during the day and will cause minimal distruptions to traffic.  Nighttime lane closures will be required during certain phases of the work.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering September 11, 2003 September 11, 2003 Complete.
Environmental Documentation Complete August 2, 2004 August 2, 2004 Complete.
Right of Way Certification June 16, 2008 April 24, 2008 Complete.
Project #1 Advertisement January 14, 2008 March 31, 2008 Complete.
Estimate Open to Traffic (Project #1) December 31, 2009 Project #1 construction is expected to be completed in June 2009.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $23.91 55.7%
Right-of-Way $ 6.78 15.8%
Construction $12.24  28.5%
Funded Project Costs $42.93 100.0%

Nickel funds included in above costs

$15.0 34.9%

2005 Transportation Partnership Account

$15.0 34.9%