Project Title & Location
SR 543 - I-5 to Canadian Border - Additional Lanes for Freight
|
Project Description
Constructs new lanes between Boblett Street and the Canadian border for a separate truck route to address congestion and safety issues on SR 543. Constructs a new interchange at "D" Street. There are currently two lanes. There will be four lanes when this project is completed.
|
|
Contractor/Consultant
David Evans & Associates are the design consultants.
|
|
Recent Progress
Documents for purchasing the additional land needed have been finalized. Real estate aquisition will begin in January.
|
|
Design Construction Impacts
Real estate aquisition will begin in January and is projected to take 22 months. If the aquisition takes as long as it is expected to, it will affect the contract advertisment date.
|
|
Environmental Impacts / Compliance
An Environmental Assessment has been completed with a finding of "no significant impact". Stormwater systems will be upgraded to modern standards. Wetland impacts will be mitigated with a replacement area within the same drainage basin.
|
Impacts to Traffic
Construction is currently planned to start in 2005 and take two years to complete. At least one lane of traffic in each direction will be maintained.
|