SR 543 - I-5 to Canadian Border - Additional Lanes for Freight

Quarterly Project Report Update for Quarter Ending June 2005

Project Title & Location
SR 543 - I-5 to Canadian Border - Additional Lanes for Freight

Project Description
Constructs new lanes between Boblett Street and the Canadian border for a separate truck route to address congestion and safety issues on SR 543. Constructs a new interchange at "D" Street. There are currently two lanes. There will be four lanes when this project is completed.

Contractor/Consultant
David Evans & Associates are the design consultants.

Recent Progress

R/W acquisition is nearly complete, with only one remaining acquisition. 

A Value Engineering (VE) study was conducted in early June to look at ways to reduce project costs and reduce the chance of problems during construction.  The study recommended several areas where cost savings may be achieved.  The feasibility of these recommendations are being analyzed by the design team. 

 

Design Construction Impacts

The project advertisement date has been revised to September 2005 to allow additional time to obtain environmental permits.

Environmental Impacts / Compliance

An initial Environmental Assessment was completed with a finding of "no significant impact" issued in Sept. 2001.  An update of the Environmental Assessment was completed in April.  The update concluded that changes that ocured since the original EA do not constitute a significant impact.

Environmental permit applications were submitted in Decemeber 2004, with permit issuance anticipated in August 2005

Stormwater systems will be upgraded to modern standards.  Wetland impacts will be mitigated with a replacement area within the same drainage basin.

Impacts to Traffic
Construction is currently planned to start spring 2006 and take two years to complete.   One lane in each direction on SR 543 will be kept open through most of the construction.  Detours will be provided when short duration closures of SR 543 are required to facilitate intersection construction.  Access to the border will be provided at all times. 

Project Milestones Scheduled Attained Milestone Outlook
Begin PE July 1998 July 1998 Completed
Environmental Documentation July 2004  April 2005  NEPA Environmental Assessment update completed April 2005
Right of Way Certification March 2005    Right of way certification anticipated immediately prior to advertisement, in September 2005.
Contract Advertisement April 2005

Advertisement delayed until September 2005 to allow more time to obtain environmental permits

Open to Traffic January 2008
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $5.4 m 16.5%
Right-of-Way $2.87 m 8.7%
Construction $24.6 m 74.8%
Funded Project Costs $32.87 m 100%

Nickel funds included in above costs

$19.1 m 58.8%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Mark Russell P.E., WSDOT Project Engineer @ (360) 788-7400 or E-mail: russelm@wsdot.wa.gov