|
Recent Progress
A Cost Risk Assessment (CRA) was completed in late August. The CRA examined numerous risk factors in the project, including among others the potential for environmental/permitting complications and rising materials costs. At this time the final results of the CRA are not yet available, but are anticipated to be ready in the next week to ten days. The results of the risk-matrix modeling and the associated impact probablities, both negative and positive, will be made available at that time.
Project design continues to steadily move ahead, focusing now on structures and finalizing the proposed alignment and associated elements. In response to comments received during the public Open House held early last spring, a fifth roundabout has been added to the project at the intersection of River Road. After conversations between WSDOT and the City of Lynden, the roundabout which had been under consideration at the intersection of Main Street in Lynden will not be added to the project. The intersection will still be widened in conjunction with the rest of the project, but a traditional traffic signal will control traffic flow. Foundation selection for the structures (the five bridges and a retaining wall) continues to evolve, as does the final preferred alternative for the Nooksack River Bridge. The recently-available geotechnical recommendations indicate very poor soils; WSDOT Bridge is now working closely with the Design Office and Pan-Geo to refine the Nooksack Bridge and foundation configuration in order to provide a final design which clear-spans the river while minimizing settlement issues stemming from poor soils.
Another Open House was held in late July for two consecutive nights, with information focused on the R/W appraisal and acquisition process highlighted at the presentation.
Appraisals in the southern half of the project are now underway, and administrative offers (AO’s) are being readied. We can expect to see the first of the appraisals completed and ready for review in September. R/W plans for the northern half of the project have been revised to reflect design decisions that were still pending in June, and are now going through the approval process. We expect approval from HQ R/W Plans Review in October/November. The southern R/W plan was revised somewhat to reflect a shift in alignment at the southern end of the project, between Tenmile Road and King Tut Road. The alignment shift was made in order to avoid impact on a parcel where the Guide Meridian Water Association wells were located. These revisions have been submitted for approval.
In response to the unexpected increase in the R/W estimate reported earlier this year, $9.8M was shifted from the CN budget to the RW budget in order to fund the anticipated costs of R/W acquisition for the entire corridor. In doing this, the project was split into two phases – Stage 1, which includes PS&E and R/W acquisition for the entire project corridor but limits construction to the 4.5 mile segment between Tenmile Road (MP 6.00) and the south edge of Lynden (MP 10.39), and Stage 2, which encompasses the construction of the remainder of the project, from MP 10.39 to Badger Road at MP 12.54.
|