SR 539 - Ten Mile Road to Badger Road Widening

Quarterly Project Report Update for Quarter Ending September 2004

Project Title & Location
SR 539 - Tenmile to International Border

Project Description
Widening Guide Meridian Road to four lanes will increase safety and traffic capacity along this heavily-traveled traffic corridor. This widening work will also provide an additional lane of traffic in each direction along a major freight corridor between Bellingham and Aldergrove, British Columbia.

Contractor/Consultant
KPFF is the design consultant

Recent Progress
KPFF was given Notice to Proceed in April 2004.  Surveying and basemapping along the corridor has been completed, and channelization design is well underway at this point.  The Value Engineering (VE) study performed in June identified methods to streamline the design and Right-of-Way (R/W) acquisition process, providing both time and possible financial savings, primarily by widening the existing roadway asymmetrically instead of symmetrically - this minimizes the total number of parcels inpacted by the widened R/W, and will provide safer, more efficient construction, while reducing impacts to traffic during construction.

Design Construction Impacts

NW Region Real Estate Services is in the process of revising the original R/W estimate of $5.3M, given the new asymmetrical configuration.  Preliminary indications point to an increase in the R/W costs, likely due to the difference in levels of available design information at the time of the original estimate and now, as well as rising property values.

Environmental Impacts / Compliance
An Environmental Assessment was completed with a finding of "no significant impact" in 1998.  These documents are being updated.   A new basin-wide approach to wetland mitigation is currently being examined for implementation on this project.

Impacts to Traffic

Traffic staging solutions will be developed during design to provide the least impact to traffic during construction.

Project Milestones Scheduled Attained Milestone Outlook
Begin PE May 2004 May2004   Preliminary engineering underway.
Right of Way Certification September 2007  
Environmental Documentation June 2005    
Contract Advertisement October 2007

 

Open to Traffic January 2010  
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $11. 8 m 13.8%
Right-of-Way $5.3 m 6.1%
Construction $68.5 m 80.1%
Funded Project Costs $85.5 m 100%

Nickel funds included in above costs

$83.9 m 98.1%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Mark Russell P.E., WSDOT Project Engineer @ (360) 788-7403 or E-mail: russelm@wsdot.wa.gov