|
Design Construction Impacts
A portion of the work has been broken out in advance of the 2007 ad date - this Phase 1 contract (consisting mainly of select clearing and earthwork, the construction of 4 stormwater ponds and 1 wetland mitigation site, as well as other preparatory work) will go to advertisement late spring 2005, avoiding a costly redesign triggered by stormwater standard changes which take effect at the end of the '05-'07 biennium. Phase 1 funding is pending final approval at this time, with full authorization expected shortly.
The omission/underestimation of some bid items from previous construction estimates, as well as underestimation of wetland buffer impacts, have increased the projected funding required for project build-out. Unexpected delays and tasks in the design process have also added somewhat to the overall project budget.
|