|
Project Title & Location
SR 539: Horton Road to Ten Mile Road Widening MP 1.67 to MP 6.26
|
Project Description
Widening Guide Meridian Road to five lanes will increase safety and traffic capacity along this heavily-traveled traffic corridor. This widening work will also provide an additional lane of traffic in each direction along a major freight corridor between Bellingham and Aldergrove, British Columbia.
|
|
Recent Progress
Necessary property acquisition is complete.
This project was originally scheduled to be constructed in two phases. Delays in acquiring a wetland mitigation site has pushed this project back into one contract. Restoration and replacement of impacted environmental elements are a permitting requirement of this project.
This contract was advertised to bidders on January 16, 2007. Bids will be opened on March 14, 2007. It is planned that work activities will start shortly after focusing on utility construction and relocation.
|
|
Environmental Impacts / Compliance
This project will provide storm water detention and treatment ponds. New wetlands will also be constructed to mitigate for impacts during construction.
Environmental permitting for the entire project is complete. Environmental issues and new wetlands discovered in the wetland redelineation completed in late 2004 have pushed the projected advertisement date out from the originally scheduled April 2005.
|
Impacts to Traffic
Staged construction will minimize traffic impacts. During construction, one lane of traffic in each direction will be open at all times. Detour routes will be provided when side roads are closed.
Roadway closures will be allowed for limited durations during night time hours. When there are roadway closures signed detours will be provided on county roads.
|