Recent Progress
Necessary property acquisition began in June 2001 and is approximately 90% complete. The remaining properties are currently in the final stages of acquisition.
This project was originally scheduled to be constructed in two phases. Delays in acquiring a wetland mitigation site has pushed this project back into one contract. Restoration and replacement of impacted environmental elements are a permitting requirement of this project. Recent updates have caused us to seek a new site where this restoration can occur.
The plans for this contract are being finalized and is scheduled to be advertised for bidding in December 2006.
A Value Engineering Study/Cost Risk Assesment was completed in May 2006 for this project. This study assisted in incorporating changes so that the scope of the work would meet the allocated budget for this project.
|