About 11,600 drivers travel this section of SR 529 each day. We repaved one mile of roadway on SR 529 along Everett's waterfront between Naval Station Everett and 10th Street.

The repaved roadway will provide a smoother, safer surface for drivers and extend the life of the roadway. We also replaced traffic sensors in the pavement and upgraded guardrail, signing and striping.

In October 2010, we advertised the project to contractors, and on December 17, 2010, we awarded the project to Lakeside Industries, Inc. of Monroe. On May 9, 2011, we began construction and wrapped up the project in July 2011.

How You Benefit
Cross GlyphImproves Safety
The repaved roadway allows drivers to travel on a smoother and safer surface without potholes and road bumps.
Dollar Sign Glyph Economic Incentive
The repaved roadway will reduce costly temporary repairs and ensure that the highway will last well into the future.

Partnerships & Cooperation
In October 2010, we advertised the project to contractors, and on December 17, 2010, we awarded the project to Lakeside Industries, Inc. of Monroe. On May 9, 2011, we began construction and wrapped up the project in July 2011.

Funding

Contact Us
Janice Fahning
WSDOT Project Engineer
Phone: (425) 225-8799
E-mail: fahninj@wsdot.wa.gov

or

Meghan Soptich Pembroke
WSDOT Communications
Phone: (206) 440-4704
E-mail: pembrom@wsdot.wa.gov

back to top