SR 522 - Snohomish River to US 2, Four Lane Widening

Quarterly Project Report Update for Quarter Ending December 2004

Project Title & Location
SR 522 - Snohomish River Bridge to U.S. 2 Widen to 4-Lane Divided Highway, Monroe

Project Description
The project will widen SR 522 to four lanes between the Snohomish River and US 2 in Monroe. The project also builds five bridges for the new roadway, including a 1/3 mile bridge across the Snohomish River.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
Selected an engineering consultant to assist with the design and WSDOT is in current contract negotiations for engineering services.

Design Construction Impacts

Surveying and wetland/sensitive area identification is the first order of work.


WSDOT will consult with various local, state, and federal regulatory agencies on the citing of the new Snohomish River bridge.

Environmental Impacts / Compliance

Mitigation efforts will include avoidance measures and adherence to state and federal permit requirements.

 

This project will construct storm water treatment facilities for both water quality and quantity.  Use of temporary erosion control measures during construction will minimize impacts.

Impacts to Traffic
Construction will start in 2009, traffic will experience narrower lanes & shoulders, slower speeds, and some advanced publicized nighttime and weekend closures may occur (detours will be provided.)  All 4 lanes should be open to traffic by summer 2012.

Project Milestones Scheduled Attained Milestone Outlook
Environmental Permits Fall 2008
Right of Way Purchased Fall 2008
Finish Contract Plans Spring 2009
Contract Advertised Spring 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $5.97 m 5.4%
Right-of-Way $5.75 m 5.2%
Construction $98.90 m 89.4%
Funded Project Costs $110.62 m 100%

Nickel funds included in above costs

$110.62 m 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Sharif Shaklawun, WSDOT Project Engineer

(206) 440-4272 or E-mail: ShaklaS@wsdot.wa.gov