SR 520 - Bridge Replacement and HOV Project

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
SR 520 Bridge Replacement and HOV Project

Project Description
The overall project will replace the SR 520 floating bridge and associated approaches. This project is currently funded to complete the environmental review, including an Environmental Impact Statement through the Record of Decision, early right-of-way acquisitions, and design.

Contractor/Consultant
EIS - Parametrix Public Involvement - EnviroIssues General Engineering - HDR

Recent Progress

Environmental and Design:

1. The Draft EIS was released for public comment in August.  The DEIS Public Hearings were held in September.  Public comment period ends October 31st

2. The Project Design team began the 10% design phase.

3. Governor’s Expert Review Panel (ERP) conducted an in-depth review of the project, findings were released to the public in September.

4. Incorporated EPR cost estimate recommendations at Governors direction.  Preliminary findings indicate increased costs generally due to inflation, market uncertainty, and potential scope changes.  Updated project cost estimates were released September 20th.

5. Continued planning for the development of a Special Projects Construction Site that could accommodate the construction of the SR520 floating bridge pontoons.  Project staff is continuing to conduct environmental and engineering data collection and evaluation.

6. Completed series of workshops with the University of Washington regarding 6-Lane design options.

7. Developing a Quieter Pavement test project on SR520.  Proposed construction in 2007.

 

Right of Way Acquisition:

Appraisals of early right of way acquisitions underway.

 

For more project information see the project web page at:

www.wsdot.wa.gov/projects/SR520bridge

 

Design Construction Impacts

The anticipated start of major construction is mid-2009.  The project has received $52 million from the 2003 Nickel Package and $500 million from the 2005 Transportation Partnership Account.  This money will be used for the completion of the Environmental Impact Statement, project design, right of way purchases and to begin construction.  Project construction depends on additional funding from tolling, a regional transportation investment, and other sources.

Environmental Impacts / Compliance

A Draft Environmental Impact Statement with a thorough analysis of the project alternatives and options was issued in August 2006.  The goal is to identify a preferred alternative after the public comment period.

Impacts to Traffic
Traffic impacts in the corridor have not yet been fully determined.  Pontoons for the new floating bridge will be constructed offsite and brought in through the Ballard Locks.  The new floating bridge will be built to the north of the existing bridge allowing traffic to continue use the exisiting bridge during construction.

Project Milestones Scheduled Attained Milestone Outlook
Start Right of Way Acquisition Spring 2004  Ongoing Appraisals of properties east of Lake Washington are underway
Start Environmental Permitting Process Summer 2005  Ongoing Permitting discussions are continuing with resource agencies.  No permits have been applied for or issued at this time.
Start Project Design Spring 2006  Spring 2006 Start of detailed project design begin in spring of 2006 and will continue through completion of the design phase of the project.
Issue Draft Environmental Impact Statement August 2006 August 2006 Draft EIS was issued in August 2006 followed by a public comment period in September.
Start Construction Summer 2009 Project construction is partially funded by the 2005 Transportation Partnership Account.  Additional revenue is needed to begin construction.  At this time construction is scheduled to being in the summer of 2009.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 168.4 29%
Right-of-Way 14.5 3%
Construction 390 68%
Funded Project Costs 572.9 100.0%

Nickel funds included in above costs

52.3 9%

2005 Transportation Partnership Account

500 87%

  For more information, go to www.wsdot.wa.gov/projects

Julie Meredith, WSDOT Engineering Manager @ (206) 381-6406 or E-mail: MeredJL@wsdot.wa.gov