Recent Progress
Recent project milestones accomplished include:
EIS Phase - 1.) held open houses in June 2004; 2.) also held Advisory and Technical Committee briefings in June 2004; 3.) fifteen draft discipline reports have been completed as of September 2004; they were all prepared in the new reader-friendly format; 4.) completed Construction Staging report for temporary bridge option; 5.) completed Bridge Operations Facility conceptual design.
Early R/W Phase - early Right of Way acquisition (UW parcel) is currently on hold. Record of Survey and existing R/W plans work is still underway and on schedule.
To get cost and descriptions of project options see the project web page at: http://www.wsdot.wa.gov/projects/SR520bridge
|