- Received legislative funding approval for replacement of the Floating Bridge
- Issued RFQ for Design Build Pontoon Construction Project
- Prepared potential NEPA strategies for phased project delivery
- Kick-off test pile project
- Completed Project Impact Plan for the west side design options
- Completion of the preliminary engineering for the Evergreen Point Bridge structures
- Design freeze for the SDEIS analysis
- Supported preparation for and attended Eastside Communities Design Collaboration
- Continued development of Eastside Design Build Action Item and Critical Milestones List
- Completed updated CEVP Cost Estimate for Pontoon Construction
- Began preparations for the SR 520 legislative workgroup which will convene next quarter