Environmental and Design:
1. Working with Co-leads to complete Draft EIS. The milestone date for issuing the DEIS is August 2006.
2. General Engineering Consultant (GEC) and project staff scoping corridor design activities, estimated start summer 2006. Expanding into new office space for additional staff.
3. Enhancing corridor Catastrophic Failure Planning, Phase 1 to be completed fall 2006.
4. Planning for the development of a Special Projects Construction Site that will accommodate the construction of the SR520 floating bridge pontoons. Conducting data collection and preliminary engineering review of potential sites complete in April. Final site selection is expected to be completed fall 2006.
5. Completed series of workshops with the University of Washington regarding 6-Lane design options. Additional working sessions underway.
7. Developing a Quieter Pavement test project on SR520. Proposed construction in 2007.
Right of Way Acquisition:
Appraisals of early right of way acquisitions underway.