Recent Progress
Recent project accomplishments include: EIS Phase
1. First drafts of all eighteen Discipline Reports now completed. Six are completed through all reviews.
2. Executive and Technical Committee Meetings, Jurisdictional Staff and Community briefings.
3. Continue to meet with the City of Seattle and Regulatory Agency’s concerning the temporary detour bridge and work trestles proposed for bridge construction in the Arboretum.
4. Continue to meet with Sound Transit and King County Metro to discuss the opportunities for both projects to make better transit and pedestrian connections between SR520 and the ST North-Link Husky Stadium Station.
Early Right of Way Phase:
1. Purchase of the selected UW parcel for Right of Way Acquisition has been deferred due to the uncertainty in future funding and the pressing need to begin advance design work. $4.0m is re-allocated to 05-07.
2. Development of a project Record of Survey and New Right of Way Plans is progressing.
To get cost and descriptions of project options see the project web page at: http://www.wsdot.wa.gov/projects/SR520bridge
|