Skip Top Navigation

SR 520 - Floating Bridge and Landings Project: What's Happening Now?

Project photos

Aerial view of the SR 520 floating bridge construction site See more photos from Lake Washington, Tacoma, and Kenmore on our Flickr site.

Updated: May 13, 2013

Construction activities for the new SR 520 floating bridge and landings are under way. Read about recent construction progress in our project update (pdf 3.2 mb).

We are currently building components for the new floating bridge at locations in Aberdeen, Tacoma and Kenmore. 

Current work


Lake Washington

Crews continue to assemble rebar for the pier columns within the cofferdam for Pier 1. In April, a 200-foot tall tower crane was installed within the cofferdam to assist with project activities.

On Pontoon W, crews continue activities to construct support columns and other structures. Two box columns enclose access stairwells for maintenance crews. The final concrete pours for these box columns was completed earlier this month.

On March 15, crews finished installing the last anchor needed for the new floating bridge. A total of 58 anchors will secure the pontoons for the new floating bridge.

Crews have resumed work activities at Pier 36 near Madison Park. This work includes the construction of work platforms and casting concrete pier columns. Pier 36 is the western-most pier for the new floating bridge.

The location of the Pier 1 cofferdam and project barges completely block the east navigation channel. This obstruction alters use of the east navigational channel and SR 520 drawspan. Read more information for boaters and SR 520 drivers.

Medina


See the latest activity on our Medina construction camera. Curious what you're looking at? Check out this guide.

On land in Medina, crews have completed construction of Pier 3, the eastern-most pier. Crews have begun to prepare the pier for installation of the new roadway.

On the south column of Pier 2, crews cast the first new roadway section for the new floating bridge in April. This roadway sits on top of tall support columns that can be seen from the existing bridge. Crews continue construction of the north column of Pier 2.


Kenmore


See the latest activity on our Kenmore construction camera. Curious what you're looking at? Check out this guide.

Construction of all anchors for the floating bridge is complete. Crews continue to construct pre-cast concrete panels for the bridge maintenance facility dock.

Construction of the new roadway deck section casting facility continues. Casting of the roadway deck sections is planned to begin in 2014.

For more information about the work planned in Kenmore, view our project page.


Tacoma


See the latest activity on our Tacoma construction camera. Curious what you're looking at? Check out this guide.

Crews are currently constructing the next cycle of pontoons. In mid-March, crews began pouring concrete for the pontoon walls. During this cycle, crews will construct eight pontoons. 

The previous cycle of pontoons was completed earlier this year. Between Jan. 29-31, a total of six pontoons were towed out of the casting basin in Tacoma. Check out photos on our Tacoma Flickr page and watch the time-lapse video on YouTube.


Grays Harbor

Crews have completed construction of the second cycle of six pontoons at the casting facility in Aberdeen. You can find more information on the Pontoon Construction Project on the project website.

Watch our YouTube video to learn more about the float-out process.