SR 520 - West Lake Sammamish Parkway to State Route 202

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
SR 520 W Lake Sammamish Parkway to SR 202 - Redmond

Project Description
This project will widen State Route 520 to eight lanes between the West Lake Sammamish Parkway Interchange and the State Route 202 Interchange. The widening includes auxiliary lanes, ramps and high occupancy vehicle (HOV) lanes.

Contractor/Consultant
CH2M-HILL was selected as the prime design consultant for this project (both Stages 3A and 3B).  Tri-State Construction has been selected as the prime construction contractor for the Flyover portion (Stage 3A).

Recent Progress

Construction for stage 3A (the flyover ramp) is in progress.

The Deviations and Channelization Plans for stage 3B were approved in July, and the Design Decision Package is being reviewed. Revisions are also being made to stormwater design to comply with new City of Redmond codes and the draft Stormwater Report has been reviewed by our Hydraulics staff. This will feed into the completion of the Biological Assessment (BA) for stage 3B of the project which is scheduled to be complete in late October.

A Design Workshop was held on July 31, 2007, with the City of Redmond and permitting agencies to discuss the stormwater design for the project and to develop a plan to move forward. Prior to the workshop, general agreement was reached with the City on floodplain storage and stormwater treatment requirements. The project will provide compensatory floodplain storage for Bear Creek within the project area right of way, and will also provide enhanced stormwater treatment within the roadway prism using the Ecology Embankment BMP followed by sheet flow dispersion through the Bear Creek buffer. This will allow the deletion of a detention vault for flow control. We are still working with the City to resolve the issue of buffer impacts to Bear Creek. WSDOT is proposing to mitigate for the permanent stream buffer impacts at an off-site location within the Bear Creek Basin and to enhance the functions of the remaining buffer within the project limits.

At the June QPR, we reported that the results of the Cost Risk Assessment performed earlier that month indicated the project was approximately $6 million over budget. Since that time, we have looked at ways to reduce the project cost and have identified a number of potential cost savings. The biggest reduction is the deletion of the detention vault at a savings of $3.7 million. In addition, the new bridges being constructed for the on and off ramps at the West Lake Sammamish Parkway Interchange have been modified to a prestressed concrete girder design. This will result in a savings of approximately $1 million, and revisions to the retaining wall design have provided another $1 million in savings.

Based on the revised estimate using the cost savings listed above, the project is currently within budget. However, we are still negotiating with the City of Redmond on the stream buffer issue. There is a risk that the Advertisement date may be delayed by as much as a year if the City Council does not approve the proposed buffer mitigation and issue a Shoreline Permit.  This will result in additional inflation costs.  We recommend that the project be placed on the watch list for the December QPR, and we will continue to monitor the costs as the PS&E is developed.

Design Construction Impacts

The Flyover ramp project will require closure of SR 202 for several nights in the vicinity of SR 520 to set bridge girders across SR 202.

Stage 3B will require lane, ramps, and roadway closures. The design team is looking into ways to minimize impact to the traveling public during the construction of stage 3B. 

Environmental Impacts / Compliance
WSDOT is working closely with City of Redmond, NMFS, USFW, and the MAP Team to provide water quality treatment and flow control for the project. The right of way constraints of Bear Creek and Marymoor Park and the low roadway elevations on SR 520 relative to the Sammamish River eliminate the use of many traditional BMPs.

Impacts to Traffic
The construction of the flyover ramp (stage 3A) is in progress. There will be intermitten lane closure on SR 202.

Night time closure of SR 202 and West Lake Sammamish Parkway will be needed to set the bridge girders during stage 3B. There will also be lane and ramp closures during stage 3B. 

Mitigation efforts will include a comprehensive public awareness campaign and implementing a detour route.

Project Milestones Scheduled Attained Milestone Outlook
Start Project Fall 2003 Yes Completed.
Environmental Documentation Spring 2006  June 2006 Completed for stage 3A.
Design Documentation Fall 2006   The Design Documentation Package for Stage 3A was approved in December 2006. The Design Documentation Package for Stage 3B is scheduled to be approved in September 2007.
Right of Way Certification Sep 2008   Right of Way is currently not required for this project.
Contract Advertised Oct 2008   Construction of Stage 3A (the flyover ramp) is in progress. Stage 3B (HOV Widening) will be advertised at the end of 2008.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $11.1 10.8%
Right-of-Way $2.6 2.5%
Construction $88.7 86.7%
Funded Project Costs $102.4 100%

Nickel funds included in above costs

$102.3 99.9%

2005 Transportation Partnership Account

None

  For more information, go to www.wsdot.wa.gov/projects

Methqal Abu-Najem, WSDOT Project Engineer @ (206) 440-4312 or E-mail: abunajm@wsdot.wa.gov