SR 519 - S Seattle Intermodal Access - Royal Brougham

Quarterly Project Report Update for Quarter Ending December 2007

Project Title & Location

SR 519/I-90 to SR 99 - Intermodal Access Project I/C Improvements

Project Description
SR 519 is an important thoroughfare for cars, freight and pedestrians in Seattle's SODO district that connects I-90 and I-5 with the Port of Seattle and Colman Ferry Dock. Roadway congestion is increased by a railroad crossing. Phase 2 of this project will determine scope, design and construct additional improvements to reduce pedestrian, car and truck congestion and increase safety and freight mobility.

Contractor/Consultant
Preliminary Engineering and Environmental Assessment by CH2M Hill.  Public Involvement by EnviroIssues.  Project Managment Assistance by Baillie and Assoc.

Recent Progress
The team has finalized the Environmental discipline reports, draft Environmental Assessment and Final Letter of No Effect.  Preliminary Engineering is near completion and the design has been presented to the Seattle Design Commission.  Geotechnical and Archeological Field investigations have begun.

Design Construction Impacts
The team is working to advance the construction of this project by utilizing a design-build procurement method. Construction completion would be accelerated from mid 2012 to end of 2010.

Environmental Impacts / Compliance
The draft Environmental Assessment will be available to the public in early February, 2008.  The April 2008 Finding of No Significance (FONSI) is on schedule.

Impacts to Traffic
The corridor will see improved traffic at the completion of the project.  Construction impacts will be minimized.  The team is working to provide a solution that will allow one lane each way on Royal Brougham to remain open.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering October 21, 2005 October 25, 2005 Beginning of Alternative Assessment
Project Definition Complete June 02, 2007 May 18, 2007  
Environmental Document Complete April 25, 2008  
Right of Way Certification March 16, 2009  
Advertisement Date April 6, 2009  
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 6.96 9.4
Right-of-Way 1.85 2.5
Construction 65.59 88.5
Funded Project Costs 74.40 100.0

Nickel funds included in above costs

57.0 76.6

2005 Transportation Partnership Account

Pending PCRF Approval

  For more information, go to www.wsdot.wa.gov/projects