SR 518 - SeaTac Airport to I-5 / I-405 Interchange

Quarterly Project Report Update for Quarter Ending March 2006

Project Title & Location
SR 518-Sea-Tac airport to I-5/I-405 interchange, in Tukwila

Project Description
This project will improve existing mobility and safety as well as accommodate projected airport traffic by adding a third eastbound lane between the North Airport Expressway and the I-5/I-405 interchange.

Contractor/Consultant
Consultants working on the SR 518 project include; Parsons Brinkerhoff, EnviroIssues, HWA, Lin & Associates, Heidi Stramm, The Resource Group, DEA Engineers, Herrera and Geoff Baillie and Associates.

Recent Progress
Held a Value Engineering Study January 2006, completed the draft channelization plans and deviations, begun work on the hydraulics design

Design Construction Impacts
The December 2005 Cost Estimate Validation Process (CEVP) estimates a construction duration of 18 to 24 months with a construction start the summer of 2007 .

Environmental Impacts / Compliance
Environmental Impacts and mitigation to be determined as part of the EA process.

Impacts to Traffic
When completed the SR 518 project will reduce congestion on eastbound SR 518 and the North Airport Expressway and eliminate the difficult merge from the North Airport Expressway and SR 99 to eastbound SR 518.

Project Milestones Scheduled Attained Milestone Outlook
Receive Geometric Design Approval May 2006 Deviations and channelization plans in review, on schedule
Obtain FONSI August 2006 On schedule
Obtain Permits February 2007 On schedule
Ad Date April 2007 On schedule
Begin Construction August 2007 On schedule
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 7 23
Right-of-Way 0.5 2
Construction 23.1 75
Funded Project Costs 30.6 100

Nickel funds included in above costs

2005 Transportation Partnership Account

20

  For more information, go to www.wsdot.wa.gov/projects