SR 510 - Yelm Loop

Quarterly Project Report Update for Quarter Ending March 2007

Project Title & Location
SR 510 - Yelm Loop

Project Description
The purpose of this project is to improve traffic circulation within the City of Yelm by routing the through traffic away from the town center. This project will construct a new 4.2 mile two-lane limited access highway, and includes two roundabouts, one signal, and a separated non-motorized pathway. The new highway will reduce congestion and improve freight mobility, safety, and traffic circulation.

Contractor/Consultant
Parametrix

Recent Progress
The document containing the findings and conclusions of the July 26, 2006 limited access hearing was adopted on December 5, 2006.  The Right of Way Plan was approved December 7, 2006, and right of way acquisition continues.  Of approximately 100 properties needed for the project, 13 parcels have been acquired, 10 parcels are currently in negotiation, and 14 are being appraised.  An additional $8 million was advanced in January 2007 from future biennium to acquire right of way from willing sellers this biennium.
NEPA re-evaluation is in progress and is expected to be completed by the end of December 2007.

Design Construction Impacts
Significant development continues along the corridor.

Environmental Impacts / Compliance

In 1999 and 2000, under the direction of the City of Yelm, a NEPA Environmental Assessment (EA) was completed.  FHWA issued a "Finding of No Significant Impact" in 2000.  The project team has been re-evaluating the various elements addressed in the original EA.  An Environmental Reevaluation/Consultation Form is being prepared per NEPA guidelines as is a Biological Assessment (BA).

In the 6/15/06 Pre-BA meeting, the services and FHWA agreed to the BA focusing on the Y3 (SR 510 Loop) portion only.

Impacts to Traffic
The proposed project will be a new corridor.  Public can expect delays during construction at areas where the new roadway intersects with existing streets.

Project Milestones Scheduled Attained Milestone Outlook
Design Start June 2004 June 2004 This was formerly a City of Yelm lead project.  Preliminary design, including updating the environmental assessment, began in June 2004.  There was a cost risk assessment in October 2004.  Design work delayed until transportation funding was approved.
Design Resumed December 2005 December 2005 In April 2005, the legislature provided additional $33 million funding for the Yelm Loop project.  Design and environmental work resumed in December 2005.  In 2005, $2.5 million in federal funds was obtained.  The Access Hearing was held July 26, 2006.
Environmental Document Complete 12/30/2007  This is the expected date for the reevaluation to be complete.
Right of Way Certification    June 2011 Early right of way acquisition in progress.  Approximately 100 property owners are being impacted.
Contract Ad The construction phase for this project is not funded.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $5.6 15.6%
Right-of-Way $30.3 84.4%
Construction $0.00  0.0%
Funded Project Costs $35.9 100%

Nickel funds included in above costs

$0.00  0.0%

2005 Transportation Partnership Account

$33.00 91.9%

  For more information, go to www.wsdot.wa.gov/projects