SR 502 - Widening From I-5 to Battle Ground

Quarterly Project Report Update for Quarter Ending September 2007

Project Title & Location
SR 502 Widening from I-5 to Battle Ground - Clark County

Project Description
Increase capacity and safety of SR 502 between NE 10th Ave and Battle Ground by increasing the number of travel lanes from two to four.

Contractor/Consultant
Project is not yet advertised or awarded.

Recent Progress
WSDOT has conducted a total of four open house meetings and attended several meetings with businesses and community members. Over the spring, the project team developed five on-corridor and two off-corridor alternatives. Each alternative was measured against a variety of criteria, including: meeting project purpose and need; meeting WSDOT design standards; driveway and intersection conflict points; travel time; business displacements; residential displacements; wetland effects; stream, pond, and lake crossings; and potential contaminated sites. By mid-June, the seven alternatives were narrowed to three and presented at the June 14 open house. After meeting with and listening to local community members, WSDOT staff decided to move forward with the single on-corridor alternative.

Design Construction Impacts
While it is too early in project development to determine the exact magnitude, the size and complexity of the project clearly indicates there will be property impacts and business impacts.  Known risks are property acquisitions, wetland impacts, storm water treatment and fish passage barriers.

Environmental Impacts / Compliance
WSDOT has started the necessary environmental studies for this project. The studies will detail the project's direct and indirect environmental impacts (natural, ecological, societal and economic) in order to guide final design and construction.

Impacts to Traffic
No issues at this time.

Project Milestones Scheduled Attained Milestone Outlook
Preliminary Engineering January 2004 May 2004 Preliminary options are being developed
Environmental Documentation Complete July 2009 No issues at this time.
Right of Way Complete October 2011 No issues at this time.
Advertisement October 2011
Operationally Complete October 2014
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $9.1 10.3%
Right-of-Way $33.1 37.7%
Construction $45.6 52.0%
Funded Project Costs $87.8 100%

Nickel funds included in above costs

$7.8 8.8%

2005 Transportation Partnership Account

$79.8 90.9%

  For more information, go to www.wsdot.wa.gov/projects

Chris Tams, Area Engineer, at (360) 759-1310, or e-mail: swGorge@wsdot.wa.gov.