SR 502 - Widening From I-5 to Battle Ground

Quarterly Project Report Update for Quarter Ending September 2004

Project Title & Location
SR 502 Widening from I-5 to Battle Ground - Clark County

Project Description
Increase capacity and safety of SR 502 between NE 10th Ave and Battle Ground by increasing the number of travel lanes from two to four.

Contractor/Consultant
Project is not yet advertised or awarded.

Recent Progress

WSDOT is beginning to obtain survey data to develop preliminary designs. In late fall, the public involvement process will begin with community leader meetings to discuss future needs.  The construction phase of this project is not funded.

Design Construction Impacts
While it is too early in project development to determine the exact magnitude, the size and complexity of the project clearly indicates there will be property impacts.

Environmental Impacts / Compliance
WSDOT started the necessary environmental study for this project but it is not yet complete. This study will detail the project's direct and indirect environmental impacts (natural, ecological, societal and economic) in order to guide final design and construction.

Impacts to Traffic
No issues at this time.

Project Milestones Scheduled Attained Milestone Outlook
Design Start January 2004 May 2004 Preliminary options are being developed
Record of Decision July 2008 No issues at this time.
Right of Way Complete July 2011 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.0 25%
Right-of-Way $12.0 75%
Construction $0.0 0$
Funded Project Costs $15.0 100%

Nickel funds included in above costs

$15.0 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Chuck Ruhsenberger, WSDOT Area Engineer, at (360) 759-1310 or e-mail: swi-5widening@wsdot.wa.gov