I-5 - SR 502 - Interchange

Quarterly Project Report Update for Quarter Ending September 2006

Project Title & Location
I-5 / SR 502 Interchange

Project Description
This new interchange, connecting I-5 to State Route 502, will reduce congestion, improve safety and provide more direct access from Interstate 5 to north Clark County and Battle Ground.

Contractor/Consultant
Project is not yet advertised or awarded.

Recent Progress
Staff review of 90% plans has been completed and this project is currently finalizing the PS&E.  WSDOT has submitted applications for federal, state, and local environmental permits and is purchasing Right of Way.  The current Project Cost Summary reflects WSDOT's construction budget increase of $ 10 million due to cost escalation.

Design Construction Impacts
The geotechnical report identified high moisture content in the native soils which makes it unsuitable as subgrade without improvement.  The contract will include two alternatives for subgrade stabilization: overexcavation and replacement with borrow material and cement modification.

Environmental Impacts / Compliance
This project will receive an individual permit from the US Army Corps of Engineers.  Approximately 20 acres of new wetland will be created to mitigate the impacts of the project.  HPA and Sect 401 Cert have been received.

Impacts to Traffic
No impacts during design.  The construction of the bridge will require 8 nighttime closures of I-5 in order to places supergirders.  The construction of the fish passable culvert will require a 5 day closure of the Gee Creek Rest Area.

Project Milestones Scheduled Attained Milestone Outlook
Design Start July 2003 July 2003 Design begun.
FONSI January 2006 October 2005 Complete
Right of Way Complete October 2006 No issues at this time.
Ad Date November 2006 Pending approved budget
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.4 6.4%
Right-of-Way $11.7 21.9%
Construction $38.23 71.7%
Funded Project Costs $43.34 81.3%

Nickel funds included in above costs

$53.34 100%

2005 Transportation Partnership Account

  For more information, go to www.wsdot.wa.gov/projects

Chris Tams, Acting Area Engineer at 360-759-1310, or e-mail: swGorge@wsdot.wa.gov.