Project Title & Location
I-5 / SR 502 Interchange
|
Project Description
This new interchange, connecting I-5 to State Route 502, will reduce congestion, improve safety and provide more direct access from Interstate 5 to north Clark County and Battle Ground.
|
|
Contractor/Consultant
Project is not yet advertised or awarded.
|
|
Recent Progress
This project is in the Preliminary Engineering and Environmental Assessment phase. The new interchange configuration is now a partial clover leaf. In February, the interchange design was modified slightly to incorporate a new loop ramp to I-5 northbound. A Findings and Order Document is being developed to address the comments recieved at the Access Hearing and there will be a public review period for this document this summer. Geotechnical drilling is complete and a geotechnical report is being prepared. The bridge design for this project is continuing.
|
|
Design Construction Impacts
Right of way acquisition, geotechnical uncertainty and storm water treatment have been identified as potential risk items. The project team is developing a risk management plan to minimize impacts to the scope, schedule and budget.
|
|
Environmental Impacts / Compliance
Parsons, Brinkerhoff, Quade & Douglas, a consultant to WSDOT, is finishing the technical reports and preparing the evironmental assessment.
|
Impacts to Traffic
No impacts during design.
|