I-5 - SR 502 - Interchange

Quarterly Project Report Update for Quarter Ending September 2003

Project Title & Location
I-5 / SR 502 Interchange

Project Description
This new interchange, connecting I-5 to State Route 502, will reduce congestion, improve safety and provide more direct access from Interstate 5 to north Clark County and Battle Ground.

Contractor/Consultant
Project is not yet advertised or awarded

Recent Progress
The Preliminary Engineering, Cost Risk Assessment, Environmental Documentation, Access Hearing, and public involvement processes have begun.  WSDOT and our consultant, Parsons, Binkerhoff, Quade, & Douglas, are teaming to conduct this initial work.  A public meeting for this project will be held on October 21, 2003.

Design Construction Impacts

Right of Way acquisition, geotechnical uncertainty, and stormwater treatment have been identified as potential risk items. The project team is developing a risk management plan to minimize impacts to the scope, schedule and budget.

Environmental Impacts / Compliance
Parsons, Brinkerhoff, Quade, & Douglas has begun the environmental documentation process. 

Impacts to Traffic
No impacts during design.

Project Milestones Scheduled Attained Milestone Outlook
Design Start July 2003 July 2003 Design begun.
Record of Decision January 2006 No issues at this time.
Right of Way Complete October 2006 No issues at this time.
Ad Date November 2006 No issues at this time.
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 2.5 7.2
Right-of-Way 4.0 11.5
Construction 28.23 81.3
Funded Project Costs 34.73 100

Nickel funds included in above costs

34.73 100

2005 Transportation Partnership Account