SR 4 / SR 401 - Roadside Safety Improvements

Quarterly Project Report Update for Quarter Ending December 2006

Project Title & Location
SR 4 and SR 401 - Roadside Safety Improvements

Project Description
To reduce collisions where motorists have driven off the roadway, SR 4 and SR 401 will be improved with new guardrail, removal of fixed objects, and improvement of roadsides. By installing guardrail and removing fixed objects, the project will reduce the severity of run-off-the highway collisions.

Contractor/Consultant

Recent Progress

Design Construction Impacts

Environmental Impacts / Compliance

Impacts to Traffic

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering Jan 2006 Jan 2006
Environmental Documentation Complete Dec 2008
Advertisement Date Feb 2009
Operationally Complete Dec 2009
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $0.16 23%
Right-of-Way
Construction $0.55 77%
Funded Project Costs $0.71 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

$0.71 100%

  For more information, go to www.wsdot.wa.gov/projects

Project costs do not reflect The Governor's 2007-09 Proposed Budget.

Casey B. Liles, WSDOT Area Engineer, (360) 905-1500 or e-mail:  swVanc@wsdot.wa.gov