SR 307 / SR 104 - Safety Corridor - Complete August 2009

Quarterly Project Report Update for Quarter Ending June 2007

Project Title & Location

SR 307/SR104 Safety Corridor – Kitsap County

Project Description
The project corridor runs from MP 0.00 to MP 5.25 on SR 307 and MP 20.58 to MP 23.70 on SR 104. This corridor is the main connector route between Poulsbo and the Kingston Ferry Dock. This project provides spot safety improvements to reduce the frequency and severity of accidents within the limits of HAC and HAL locations. These improvements include the installation of guardrail, slope flattening and sight distance improvements, and the re-alignment of the Port Gamble Road intersection.

Contractor/Consultant
This project is currently in the Scoping Phase.  The Design Phase is scheduled to begin in December 2007.

Recent Progress

The Design Matrix parameters and collision data have been evaluated for the corridor. Based on the data, a benefit/cost analysis was done on the Big Valley/Little Valley intersection, Port Gamble intersection, and proposed guardrail installation. As a result of the benefit/cost analysis, the project office prioritized proposed improvements and is proceeding with a proposed design for concurrence.

Design Construction Impacts
Right-of-way acquisition will be necessary at the Port Gamble Road intersection to realign the roadway, widen for channelization, and provide wetland mitigation. It is anticipated that approximately four parcels will be affected.
Sight distance and radii improvements will be made throughout the project where right of way and wetlands allow.

Environmental Impacts / Compliance
From approximately milepost 0.50 to milepost 1.58 on SR307, Dogfish creek is immediately adjacent to the roadway. Guardrail will be installed with techniques to minimize impacts to the creek. Wetlands occur east of the Port Gamble intersection (milepost 4.53 on SR307). The realignment of the intersection will be designed to minimize wetland impacts.

Impacts to Traffic
During construction there will be lane restrictions and possible lane closures at the Port Gamble Road intersection. Night work will be specified to minimize impacts.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering  January 17, 2006 Currently on track.
Environmental Documentation Complete June 15, 2007 This is delayed to January 31, 2008.  Design is currently being refined to avoid and minimize imacts to sensitive resources.  The design must be finalized to define the type and schedule of the environmental document.  This delay will not impact the rest of the delivery schedule.
Right of Way Certification October 3, 2008
Contract Advertisement November 3, 2008
Open to Traffic October 28, 2010
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $1.00 20%
Right-of-Way $1.00 20%
Construction $3.00 60%
Funded Project Costs $5.00 100%

Nickel funds included in above costs

2005 Transportation Partnership Account

$5.00 100%

  For more information, go to www.wsdot.wa.gov/projects