SR 305 - Poulsbo South City Limit to Bond Road

Status

Complete

Two new SR 305 lanes open in Poulsbo

Construction is complete and all lanes are open on the State Route 305 widening project between Hostmark Street and Bond Road.

The project added lanes with peak hour high occupancy vehicle (HOV) designation, improved five intersections and installed bike lanes.

WSDOT, along with its partners, the State Transportation Improvement Board (TIB) and City of Poulsbo, awarded the project to contractor Stan Palmer Construction, Inc. for its bid of $14.9 million. 

The Salmon Have Spoken: Realignment of Dogfish Creek a Success 

More information on the project and its funding challenges.

Why is WSDOT proposing this project?
The State Route 305 corridor is a vital transportation link for western Washington, and the Puget Sound region. SR 305 traffic volumes through Poulsbo have steadily increased in recent years, substantially increasing congestion.

This project will relieve traffic congestion and improve pedestrian and bicycle movements.

The End Result
WSDOT will widen SR 305 from Hostmark Street vicinity to Bond Road (milepost 11.17 to 13.23). The project includes the following:

  • Two new traffic lanes (one in each direction) signed as High Occupancy Vehicle (HOV) lanes during peak commuter hours on weekdays and as general-purpose lanes off-peak and on weekends.
     
  • Turning lanes were improved at Bond Road, Forest Rock Lane, Liberty Road, Lincoln Drive and Hostmark Street.
     
  • Bicycle lanes were also provided.
     
  • Sidewalks were constructed between Harrison Street and Lincoln Drive.

Project Benefits

  • Safety. The project adds sidewalks and bicycle lanes, as well as turning lanes at five intersections.
  • Congestion relief. The use of HOV lanes will help traffic flows during peak commuting hours. Emergency vehicles will be able to respond to incidents much quicker due to the additional lanes.

What is the project timeline?
Development of the environmental documentation was completed in the spring 2005. At that time applications for environmental permits and purchasing right of way began.

Design work was finalized and the project advertised for construction. Bid opening occurred June 1 and Stan Palmer Construction Inc. was awarded the bid for $14.9 million.

Construction on the highway was completed in September 2008.  Planting at culvert ends and the wetland mitigation site has been completed.

Financial Information
This project is funded through the following sources:

  • Existing Funds : $27,234,800
  • Other Agency Funds : $10,315,638;
  • City of Poulsbo ($1,046), Olhava Associates L.P. ($5,603,798), Transportation Improvement Board - TIB ($4,272,000), City of Poulsbo - TIB Match ($427,200), Sprint ($11,594)
  • Total Funding Available From All Sources : $37,550,438

How can I get more information?
Contact:
Jerry D. Moore, Project Manager
WSDOT Port Angeles Engineer Office
1707 South C Street
Port Angeles, WA 98363
Phone: 360-565-0620 or 1-877-713-7584
E-mail: moorejd@wsdot.wa.gov

back to top