Project Title & Location
SR 305 / Hostmark St. Vicinity to Bond Rd. - HOV Lanes
|
Project Description
This project is a mobility improvement and pavement preservation project. Mobility improvement includes the addition of two HOV lanes and intersection upgrades to increase traffic capacity. Pavement preservation consists of overlaying the roadway with HMA. A secondary benefit is the project eliminates 8 fish barrier culverts.
|
|
Contractor/Consultant
Stan Palmer Construction, Inc. was awarded this contract on 6/19/06.
|
|
Recent Progress
Paving work is in progress and work continues on the various items around the project.
|
|
Design Construction Impacts
The project is 85% complete.
|
|
Environmental Impacts / Compliance
The site is temporarily stabilized. Water quality monitoring and weekly site inspections are on-going.
|
Impacts to Traffic
All HOV and general purpose lanes are open to traffic. Shoulder and HOV lane closures are taken during the day and the existing lanes and intersections closures are taken at night.
|