Project Title & Location
SR 303/Manette Bridge Replacement - Kitsap County
|
Project Description
The purpose of this project is to replace the Manette Bridge in Bremerton. This bridge is currently structurally deficient and functionally obsolete. The new bridge will provide two 11 ft lanes, two 5 ft shoulders, and one 12 ft wide sidewalk.
|
|
Environmental Impacts / Compliance
Stormwater will be collected and treated in accordance with current standards. The majority of the work will be in- or above-water work. Several environmental permits are required for this project: Corps of Engineers section 404, Nationwide COE, Coast Guard, BA NEPS CDE, and SEPA DNS.
|
Impacts to Traffic
The public can expect periodic lane closures and slow-moving traffic through the work zone during construction. The bridge will be closed up to three months to tie the ends of the bridge into the existing streets. The public will be provided advance notice of the closure and a detour will be established.
|