SR 303 - Manette Bridge Bremerton Vicinity - Bridge Replacement

Quarterly Project Report Update for Quarter Ending June 2008

Project Title & Location
SR 303/Manette Bridge Replacement - Kitsap County

Project Description
The purpose of this project is to replace the Manette Bridge in Bremerton. This bridge is currently structurally deficient and functionally obsolete. The new bridge will provide two 11 ft lanes, two 5 ft shoulders, and one 12 ft wide sidewalk.

Contractor/Consultant
Project not yet advertised or awarded.

Recent Progress
Environmental studies are continuing.  A Biological Assessment in compliance with the Endangered Species Act was submitted to USFWS and NOAA NMFS in January 2008.  A SEPA Determination of Non-Significance was issued in March 2008.  Final bridge design is underway and is scheduled to be completed by March 2010, with an anticipated construction start in Summer 2010.

Updates to the construction cost estimate have shown that the project costs have increased significantly since the previous cost estimate in 2001. This increase is due to unusually high construction cost escalation seen in the last few years. As a result of the cost increase, some of the aesthetic concepts presented in previous public meetings are no longer included as part of this project.  WSDOT will continue to work with the community and support their efforts to secure additional funding for aesthetic enhancements.

Design Construction Impacts
Bridge construction and demolition methods will be greatly influenced by environmental considerations and permit conditions based on the site in Port Washington Narrows.

Environmental Impacts / Compliance
Stormwater will be collected and treated in accordance with current standards. The majority of the work will be in- or above-water work. Several environmental permits are required for this project, including: Corps of Engineers Section 404, Coast Guard, Section 401 Water Quality Certification, Shoreline, and a Coastal Zone Management certificate

Impacts to Traffic
The majority of the new bridge will be constructed while the existing bridge is still in use.  Nighttime closures of the existing bridge are expected, and occasional lane closures and slow-moving traffic through the work zone are expected during construction. The bridge will be closed to traffic for up to three months to complete construction of both ends of the bridge including connections to the existing streets.

Project Milestones Scheduled Attained Milestone Outlook
Begin Preliminary Engineering September 30, 1996 December 13, 2004 Design resumed December 13, 2004.  The VE Study recommendations have been evaluated and incorporated in the project design as of 11/14/2005.  The bridge design will be completed by October 2009.
Environmental Documentation Complete December 05, 2007 The Environmental Documentation and Permits are being coordinated with the resource agencies.
Right of Way Certification December 2009
Contract Advertisement March 1, 2010
Open to Traffic November 2013
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering $3.47 4.18%
Right-of-Way  $1.45  1.74%
Construction $78.24 94.07%
Funded Project Costs $83.17 100%

Nickel funds included in above costs

 

2005 Transportation Partnership Account

   

  For more information, go to www.wsdot.wa.gov/projects

Bill Elliott, Project Engineer, (360) 357-2682