SR 3 - Belfair Bypass - New Alignment

Quarterly Project Report Update for Quarter Ending March 2007

Project Title & Location
SR 3 - Belfair Bypass - New Alignment

Project Description
The proposed Belfair Bypass solves both the immediate and long-range transportation safety and mobility needs of the SR 3 corridor in northeast Mason County.

Contractor/Consultant
Skillings-Connolly, Inc. Consulting Engineers

Recent Progress

The project office had an open-house on January 9th to present the revised bypass alignment and connection alternatives. Information gathered from survey and comment forms from the open-house is being compiled to quantify trends or preferences for alternatives. This information is being applied to the decision matrix along with other selection criteria such as environmental and social impacts, cost, operational considerations and future expansion or staging to compare the connection alternatives. Presentations to other local groups and neighborhood associations are on-going.

An alternative selection is targeted for spring/summer 2007. Development of the detailed project schedule is under way. Cost estimates for each of the alternative combinations has been developed and relayed to WSDOT managers and elected officials.

Design Construction Impacts
N/A

Environmental Impacts / Compliance
Will be evaluated and determined as a result of environmental studies and preliminary design.

Impacts to Traffic
This project, which constructs a new corridor, will bisect the Alta-Vista neighborhood. A system of frontage roads will be required to provide access. It is Mason County and WSDOT's goal to complete this new road before sewer and widening work in the Belfair Urban area begins.

Project Milestones Scheduled Attained Milestone Outlook
Consultant chosen to complete Environmental Assessment March 15, 2006 This was formerly a county lead project and the scope is not completely defined.  Future milestones and complete phase costs are still being developed.
Open House to Present Alternatives January 9, 2007 January 9, 2007 Received comments and suggestions from open house to show public preference for alternatives.
Present Selected Alternative to Public Summer 2007
Project Cost Summary: Dollars in
millions
Percent
of Total

Planned vs. Actual Expenditures
(Total Project Cost)
Project Expenditure Chart

Preliminary Engineering 10.0 66.7 %
Right-of-Way 5.0 33.3 %
Construction 0.0 0.0%
Funded Project Costs 15.0 100.0%

Nickel funds included in above costs

0.0 0.0%

2005 Transportation Partnership Account

15.0 100.0%

  For more information, go to www.wsdot.wa.gov/projects

Michele Britton , Project Engineer, (360) 570-6606