Recent Progress
The Preferred Alternative Connections have been selected for preliminary design and environmental study. A connector on the north end near Lake Flora Road (N3) and another south of the North Mason School District (S4) will make the bypass the primary route for SR3 traffic.
Site survey of the 5 mile corridor is under way and is approximately 50% complete.
A draft scope of work has been developed for the consultant selected to prepare the Environmental Assessment. Negotiations of hours are proceeding. Preliminary engineering project management plan and schedule under development.
|
|
Environmental Impacts / Compliance
Will be evaluated and determined as a result of environmental studies and preliminary design.
|
Impacts to Traffic
This project, which constructs a new corridor, will bisect the Alta-Vista neighborhood. A system of frontage roads will be required to provide access. It is Mason County and WSDOT's desire to complete this new road before sewer and widening work in the Belfair Urban area begins, however construction funding must be approved by the Legislature.
|